REHABILITATION OF TISZASIGET-ĐALA CROSS-BORDER CONNECTING ROAD
Total budget: 1.735.460,00 €
Lead beneficiery NIF Zrt.: 849.975,00 €
Project partner JP ZUV: 885.485,00 €
Own contribution: 132.822,75 €
Community funding (IPA) 85%: 752.662,25 €
Project duration: 18 months
Section leinght: 2675 m
LEAD BENEFICIERY:
Nemzeti Infrastruktúra Fejlesztő Zrt.
1134 Budapest, Váci út 45
www.nif.hu
PROJECT PARTNER
JP Zavod za urbanizam Vojvodine
21000 Novi Sad, Željeznička 6/ III
www.zavurbvo.rs
REHABILITATION OF TISZASIGET-ĐALA CROSS-BORDER CONNECTING ROAD
HUSRB/1203/111/050
The territory of the Municipality of Novi Kneževac
The Rehabilitation of Tiszasiget-Đala cross-border connecting road has been approved by the National Development Agency of Hungary, which was the governing body for the IPA Cross border cooperation between the Republic of Hungary and the Republic of Serbia. The project approval No. V/40/1-1190/2012/K/1 arrived on October 25, 2012.
The rehabilitation works for the sections of total length of 2675 m had been fully approved by Novi Kneževac municipality and the Municipal Construction Directorate.
PE Urban and Spatial Planning Institute of Vojvodina has signed a PROTOCOL on the implementation and the financing of the Projects with the PE Roads of Serbia from Belgrade. This protocol confirmed the existance of the project technical documentation (Main project design) and defined the mode of financing the Project and the expert supervision of the construction works.
For the purpose of the rehabilitation works, the PE Roads of Serbia has entitled the PE Urban and Spatial Planning Institute of Vojvodina to apply for construction papers and financing of works as a project leader for the road section technical documentation provision on the first call for IPA projects.